The Clean Up Begins

With only 9 weekends to go before the  2018 running season starts on 24th March, we have a lot of cleaning and tidying up to do before the first train pulls into the station. This weekend we started on the outside of the station building, clearing the leaves off the top of the canopy using a brush head and rope mechanism we put together and used successfully last winter. Work also started on the cleaning up of the garden area next to the waiting room, which, just like the rest of the platform received its fair share of leaf’s this year!

Work on the 2nd platform is due to commence again, a couple of the shutters used for the main foundation wall are being modified to enable the North & South Ramp down to be poured in a couple of weeks time weather permitting.  It is hoped to get the platform wall completed as quickly as possible so that work can start on the footbridge foundations. Further updates to follow over the next few weeks.

Last 2017 Weekend Update

The retaining wall for the 2nd platform is almost complete now just the two ramps at either end to be constructed and it will be on to the next stage of the platform build.  As the year comes to an end the Christmas decorations have now been taken down in readiness for the spring cleanup of the station building – inside and out! over the coming weeks.

Weekend Update

Most of the day was spent de-icing the platform again! During the course of the week it had snowed and rained creating an ice rink of a platform. Thankfully the Santa Specials were not impacted to much and with a bit of careful marshalling all went off okay.

2nd Platform Update

The platform retaining wall is now close to completion. A huge 60m plus section is now visible since the shutters had been remove from the previous concrete pour the previous week.  There are two sections towards the south end of the station still to be poured along with the ramps down to  either end of the platform. The next phase will be to reshape the embankment and fill in to the rear of the wall in preparation for laying the copes.

A Cold Frosty Morning

As last week’s  post, during the Santa specials season, maintenance tasks have to fit around the arrivals and departures of the Specials, but by getting to the station early we at least get the opportunity to see the Railtour stock of carriages returning from its final run of the year being pulled by Class37 37703.  Last winter we left it a little later to clear the embankment and had to tread very carefully to prevent damaged to the spring bulbs, so this winter we decided it would be a good exercise to do in-between the Santa Specials. Hopefully the spring flowers will look even better in 2018!

 

 

2nd Platform Development

Four more sections of the platform foundation wall were poured this week, which leaves 4 more pours to complete plus the two ramps at either end.  Work has progressed well and all the guys involved deserve a huge pat on the back for what has been achieved to date.


 

Weekend Update

While the Santa specials are running work along the platform other than preparing for the first train of the day is limited, so we performed a trail vegetation clearance along the meadow walk, as suspected it is mainly brambles and overgrow bracken which will hold good for clearing the rest of the area during January & February 2018

 

Festive Festoons

With approximately 20 minutes to spare before the first Santa Special of the season arrived we finally got the last of the decorations up including the long awaited 240v festoon lights which replaced the LED festoon’s used last year which unfortunately where not bright enough. The LED lights  will be put to good use and fitted in the waiting room to add extra colour.

The Monday / Civils squad had also been at work on the 2nd platform preparing for the next concrete pour.  It is now taking shape very nicely a bit like the Queens Crossing filling the gaps between the piers!

  

 

 

2nd Platform Update

The Monday / Civils squad where out in force again during the week, focus was on the next pour of 4 sections one of which was to join up the two at the proposed footbridge is to be installed. Once set it will allow the footbridge foundation work to start.

Also taking place is the replacement of worn out sleepers along the loop section. The sleepers, many came from Kincardine Power Station and Livingston back in the early 80’s have suffered by the soggy conditions over the past 20 plus years.

Weekend Update

Ground preparation & Bulb planting continued to the North East embankment and work commenced on the west side clearing vegetation from the bridge down to the embankment.

Meanwhile during the week work continued on the 2nd Platform construction, the shutters removed from the first four sections and re installed ready for the next concrete pour week commencing 13th November.