The platform retaining wall is now close to completion. A huge 60m plus section is now visible since the shutters had been remove from the previous concrete pour the previous week. There are two sections towards the south end of the station still to be poured along with the ramps down to either end of the platform. The next phase will be to reshape the embankment and fill in to the rear of the wall in preparation for laying the copes.