Ground preparation & Bulb planting continued to the North East embankment and work commenced on the west side clearing vegetation from the bridge down to the embankment.
Meanwhile during the week work continued on the 2nd Platform construction, the shutters removed from the first four sections and re installed ready for the next concrete pour week commencing 13th November.