‘Beast of the East’ Finally Away

Snow then snow drifts followed by freezing temperatures and strong winds played havoc with access to the station and put a temporary stop to the plans of getting the final cleaning up of the station done before the first running day. However, after a quick scouting trip yesterday, we managed to get through via the top road with an attempt to get back on track. Focus was on the main waiting / exhibition room and the repainting of the floor which we managed to get finished.  The toilet room area still needs to be done, but at least the main room has a good spring clean.

Weekend Update

The garden retaining wall along the platform has now been cleaned up fully and washed down with disinfectant to hopefully hold back the moss that likes to wall as a home.  Work has now commenced on washing down the picket fence which also likes to attract the green stuff!!

Mid Week Update

Work continued on cleaning up the garden retaining wall along the platform and around the Lamp Hut. Good progress has been made and its hoped to have completed the clean up during the weekend shift.

Students & Lecturers / Supervisors from Napier University’s Civil Engineering Department were using Birkhill as their base during, what has become, an annual volunteering activity. This year they have been working up at the viaduct just south of Birkhill.  Below are some of the many volunteers getting onto the works train at Birkhill.

Wheelbarrow Derby Weekend

Work continued on clearing the leaves from the embankment slopes and garden area and giving the retaining wall a really good scrub and wash down. The wall in particular is looking good now that the vegetation has been cut back into the planting areas. Another couple of sessions will be needed to complete this task as long as the barrows last out!

Before…………

After…………….

Mid Week Update 15th Feb

Work recommenced on the platform embankment, although many of the leaves from embankment had been removed (several times) the lower level of the embankment is requiring attention again. Working from both ends of the platform, focus was the planting area and in particularly the retaining wall. It is hope to have this element of work done by the end of the weekend shift.

Platform 2 Update

The Monday crew along with the works train was up at Birkhill again to remove the shutters to recently poured north ramp, all remaining shutters have now been recovered leaving just the South facing ramp to complete. Work continues on the preparation of the footbridge foundations on both sides of the ramp which will be the main focus for the next few weeks.

  

Waiting Room Done & the Snowdrops are out!

The final job of sprucing up the waiting room has now completed, after the pictures had been hung on the walls the final task was to repaint the floor, the knees are a little tender but hopefully it was all worth it. Whilst the paint is left to dry work recommenced on the embankment garden which will be the focus for the next couple of sessions before we commence to cleaning up the exhibition room and exterior paint.

    

One of the many great points of working as a volunteer at Birkhill is the chance to see track movements and this weekend was no exception providing a glimpse of the ten Royal Scotsman coaches being transported down to Bo’ness from Manuel top and tailed by two of the BK&R diesels

 

Birkhill Group Jan 2018 Newsletter

To complement the weekly posts we are introducing a regular newsletter, which hopefully you will find interesting.  It is the intent to provide information about work being performed by other volunteer teams such as civils and S&T at Birkhill. Within the newsletter there will also be articles relating to the history of Birkhill and the development of the line through the station. Click on the link below to view our first ever newsletter. The newsletter will also be selectable under its own link towards the bottom of the web pages too. We hope you will enjoy.

Birkhill Group Newsletter Jan 2018

Weekend Update

Work continued on the sprucing up of the waiting room, all walls and ceiling have been repainted along with the cornice and skirting boards. The benches are the only thing left to touch up, before washing down and repainting the floor. The work has progressed well and is now ahead of our schedule due to putting a couple of mid week shifts in.

Weekly Update

The big clean up moved in side on Saturday 20th – work started on giving the side waiting room a well deserved bit of attention, the main focus was the touching up of the wall’s and ceilings which got scuffed during the 2017 running season, a couple more weekend sessions and it should be ready to welcome visitors at the end of March.

Meanwhile on Monday 22nd the Platform 2 squad braved the wintery weather to continue with finial bit of work for the platform foundation wall by delivering and fitting of the ramp shutter sections to the north end of the new platform and the removal of the shutters from around last concrete poor.  Weather permitting work will be ongoing during the course of February & March. More updates to follow.