The Monday / Civils squad where out in force again during the week, focus was on the next pour of 4 sections one of which was to join up the two at the proposed footbridge is to be installed. Once set it will allow the footbridge foundation work to start.
Also taking place is the replacement of worn out sleepers along the loop section. The sleepers, many came from Kincardine Power Station and Livingston back in the early 80’s have suffered by the soggy conditions over the past 20 plus years.