on 25th June, the Monday squad was back in action and have now poured the concrete for the footbridge foundations, the last remaining section of the 2nd platform and also for the signalling system at the north end of the new platform.
The squad was also kind enough to deliver a couple of dozen surplus kerbstones from the yard down in Bo’ness for the Birkhill Group’s next mini project at the south end of platform 1. The intent is to create an edging to the embankment, however, with the glorious hot weather moving and positioning the stones into place is a challenge but the kerb edging is progressing despite the heat and little swarms of flies ‘we’ appear to attract!