Birkhill 2nd Platform Update

The complete length of the 2nd platform has now been dug out and the concrete for the retaining wall foundation poured.  Additional drainage has been added also. The next step is to make up the shutters for the wall pouring exercise these are to be done down in Bo’ness and brought to Birkhill on the works train.